A UK non-profit organisation planned datacenter move within the next 12 months. The required an understanding of their environment, the servers, applications and storage. Their main focus was on Production, DMZ and Disaster Recovery.

A successful proof of concept had been carried out prior and they were ready for deployment of the ITAM scanning solution.

A workshop was conducted to assess their capabilities and readiness as well as determine how the solution would be deployed. This results in a Solution Design and commencement of the deployment of scanning.

The client also required modelling of their application architecture in preparation, so they could understand the dependencies for the move. As well as delivering on these requirements within a six week timeframe, I was able to provide additional value by identifying approximately 100 Windows servers that were out of compliance.